Tally Prime Job Costing Assignment with Question

 



Business Scenario for Job Costing


Transactions


01-Apr-2025: Materials

purchased from Flora

Enterprises:


1) Grass Rolls: 1000 units @ Rs150


2) Decorative Plants: 500 units @ Rs200


3) Fertilizers: 200 kg @ ₹50


Total Material Cost: ₹2,60,000


01-May-2025: Received ₹10,00,000 from client as Advance.


15-May-2025: Transport charges paid - ₹38,000


15-May-2025: Wages paid - ₹28,000


15-May-2025: Fuel Expenses- Rs 25000


30-May-2025: Salaries paid - ₹58,000


30-May-2025: Labour Charges paid- ₹25,000


30-May-2025: Wages paid- ₹31000


31-5-25: Material consumed by 31-May-2025:


1) Grass Rolls: 900 units


2) Decorative Plants: 450 units


3) Fertilizers: 200 kg


31-05-25: Raised invoice for the same as contract work.


Question


1) What is total amount of Profit/Loss after the completion of the project?


a) 1450000


b) 1134000


c) 1060000


d) 1432000


e) None Of the Above


2. What is the total amount of expenses incurred on Garden Landscaping Project after completion?


a) 218900


b) 214500


c) 272000


d) 205000


e) None of the above


3. What is the total amount of stock left over after the project completion?


a) 25000


b) 23500


c) 23200


d) 26000


None of the Above


4. What is the total quantity left for Decorative Plants after the project completion?


a) 40


b) 45


c) 55


d) 50


e) None Of the Above